PRJ-2412 · 2024
Katy middle school summer reroof
Two-ply cold-applied SBS over a middle school, finished nine days before teachers returned.
- Area
- 121,000 sq ft
- Duration
- 10 weeks
- System
- Mod bit
- Location
- Katy
Before and after


Drag the handle to compare. Photos are representative samples.
The challenge
A ten-week window, summer storms and a gymnasium roof with 40 ft eave heights.
Our approach
- Crew count planned backwards from the August start date
- Cold-applied system to avoid torch work
- Two crane mobilizations to cut gym lift time
- Weekly progress reports to the district PM
9 daysahead of schedule
121Ksq ft completed
20 yrNDL warranty (sample)