PRJ-2412 · 2024

Katy middle school summer reroof

Two-ply cold-applied SBS over a middle school, finished nine days before teachers returned.

Area
121,000 sq ft
Duration
10 weeks
System
Mod bit
Location
Katy

Before and after

Katy middle school summer reroof before work
Katy middle school summer reroof after completion

Drag the handle to compare. Photos are representative samples.

The challenge

A ten-week window, summer storms and a gymnasium roof with 40 ft eave heights.

Our approach

  • Crew count planned backwards from the August start date
  • Cold-applied system to avoid torch work
  • Two crane mobilizations to cut gym lift time
  • Weekly progress reports to the district PM
9 daysahead of schedule
121Ksq ft completed
20 yrNDL warranty (sample)

More case studies

Other recent work across Greater Houston.

Start a project like this

We have installed modified bitumen on buildings like yours. Let us survey the roof.

Free roof survey · Written proposal in 5 to 7 business days (sample)

Cookie preferences

Choose which cookies you allow. You can change this at any time from the link in the footer.