Clinton Drive distribution center reroof
Tear-off of a leaking BUR roof and new 60 mil TPO with tapered insulation over a 24-hour cross-dock.
- Area
- 412,000 sq ft
- Duration
- 9 weeks
- System
- TPO
- Location
- Houston
Before and after


Drag the handle to compare. Photos are representative samples.
The challenge
The building ran three shifts with 118 dock doors, and 40 percent of the old roof insulation was wet.
Our approach
- Infrared survey mapped 164,000 sq ft of wet insulation for removal
- Crane picks scheduled at 5:30 am shift change on the non-dock side
- Tapered polyiso rebuilt slopes to 32 drains
- Daily dry-in sections of 7,000 to 9,000 sq ft
They built the schedule around our trucks instead of asking us to work around their crane.